Progress Update, Week of April 17th, 2023
During the week of April 17, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of April 17, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of April 10, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of June 20, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge.
During the week of June 13, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge.
During the week of June 6, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge.
INTRODUCTION The Gowanus Remediation Team (GRT) continues with the dredging of soft sediments from RTA-1 under the oversight of the EPA. The dredge material is… Read More »Cultural Resources Review Results #20, May 12, 2022
uring the week of May 30 the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge. Daily closures were in effect during work between bridge abutments.
During the week of May 23 the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) north of Union Street.
During the week of May 16 the Gowanus Remediation Team (GRT) resumed In Situ Stabilization (ISS) north of Union Street.
During the week of May 2 the Gowanus Remediation Team (GRT) completed Phase 2 dredging near the Union Street Bridge. Sediment was raked following the completion of dredging activities.