Progress Update, Week of June 12th, 2023

  • by

During the week of June 12, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material was placed between the headwall and Carroll Street.

Progress Update, Week of June 5th, 2023

  • by

During the week of June 5, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement began between Union Street and Carroll Street.

Now Live: The Gowanus Transformation Through Generations Storymap