Skip to content

Updates

Progress Update, Week of September 11th, 2023

  • by

During the week of September 11, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement was completed using the low velocity spreader barge.

Progress Update, Week of September 4th, 2023

  • by

During the week of September 4, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.

Progress Update, Week of August 28th, 2023

  • by

During the week of August 28, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.

Progress Update, Week of August 21st, 2023

  • by

During the week of August 21, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Union Street and 3rd Street.