Progress Update, Week of March 27th, 2023
During the week of March 27th and following performance of the demonstration test for the RTA1 capping operation, the full scale capping began at target areas within RTA 1.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of March 27th and following performance of the demonstration test for the RTA1 capping operation, the full scale capping began at target areas within RTA 1.
During the week of March 20, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation.
During the week of March 13, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation.
During the week of March 6, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation.
During the week of February 27, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation
To contact the Gowanus Remediation Team please email info@gowanussuperfund.com or call the hotline at (718) 569-5762.