Progress Update, Week of April 12, 2021
During the week of April 12 the Gowanus Remediation Team continued working along the canal.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of April 12 the Gowanus Remediation Team continued working along the canal.
During the week of April 5 the Gowanus Remediation Team continued working along the canal.
During the week of March 29 the Gowanus Remediation Team continued pin pile installation and dredging along the canal.
During the week of March 22, the Gowanus Remediation Team continued work along the canal.
During the week of March 15, the Gowanus Remediation Team continued work along the canal.
To contact the Gowanus Remediation Team please email info@gowanussuperfund.com or call the hotline at (718) 569-5762.