Progress Update, Week of May 9th, 2022
During the week of May 2 the Gowanus Remediation Team (GRT) completed Phase 2 dredging near the Union Street Bridge. Sediment was raked following the completion of dredging activities.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of May 2 the Gowanus Remediation Team (GRT) completed Phase 2 dredging near the Union Street Bridge. Sediment was raked following the completion of dredging activities.
During the week of May 2 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge.
During the week of April 25 the Gowanus Remediation Team (GRT) continued phase 2 dredging near the Union Street Bridge.
During the week of April 18 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge.
During the week of April 11 the Gowanus Remediation Team (GRT) conducted In-Situ Stabilization (ISS) near the Carroll Street Bridge early in the week, before temporarily suspending ISS operations in order to commence Phase 2 dredging.