Progress Update, Week of May 16th, 2022
During the week of May 16 the Gowanus Remediation Team (GRT) resumed In Situ Stabilization (ISS) north of Union Street.
During the week of May 16 the Gowanus Remediation Team (GRT) resumed In Situ Stabilization (ISS) north of Union Street.
During the week of May 2 the Gowanus Remediation Team (GRT) completed Phase 2 dredging near the Union Street Bridge. Sediment was raked following the completion of dredging activities.
During the week of May 2 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge.
During the week of April 25 the Gowanus Remediation Team (GRT) continued phase 2 dredging near the Union Street Bridge.
During the week of April 18 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge.
During the week of April 11 the Gowanus Remediation Team (GRT) conducted In-Situ Stabilization (ISS) near the Carroll Street Bridge early in the week, before temporarily suspending ISS operations in order to commence Phase 2 dredging.
During the week of April 4 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Carroll Street Bridge.
During the week of March 28 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS). The ISS work barges were relocated to conduct ISS near the Carroll Street Bridge.
During the week of March 21 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge. At Degraw Street the tieback installations… Read More »Progress Update, Week of March 21st, 2022
During the week of March 14 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.