Gowanus TB4 Weekly Progress Report – October 6, 2017
The weekly progress report for the week ending October 6 is now available for review.
The weekly progress report for the week ending October 6 is now available for review.
The second phase of work, referred to as the Dredging and Capping Pilot Study, includes dredging contaminated sediment from the turning basin and installing a… Read More »October 2017 Update – 4th Street Turning Basin Dredging and Capping Pilot Study
Over the past few weeks, the Design Team and its contractors continued efforts on three areas of study which began earlier this year. These three… Read More »September Update
The Design Team and its contractors remain engaged in several activities on or near the canal. Drilling for Bulkhead Study In August, the field team… Read More »August Update
The Design Team and its contractors continue working on several projects on the canal. Drilling for Bulkhead Study: As part of EPA’s remedy, dredging will be… Read More »July Update
The Design Team and its contractors remain engaged in several activities on the canal as the warm summer weather continues. Drilling for Bulkhead Study: As… Read More »June Update
As the spring weather continues, the Design Team and its contractors remain engaged in several activities on the canal. Upcoming Work Groundwater Studies: We will… Read More »May Update
As the spring weather continues, the Design Team and its contractors remain engaged in several activities on the canal. Upcoming Work Sediment Studies: We will… Read More »April Update
The design team is preparing for a debris removal pilot study, scheduled to begin in the summer of 2016. The pilot study will take place… Read More »March 2016 Update
The Design Team and its contractors are currently engaged in several activities on the canal. These activities are part of their ongoing effort to further… Read More »March Update