Progress Update, Week of October 11, 2021
During the week of October 11 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.
During the week of October 11 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.
During the week of October 4 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.
During the week of September 27 the Gowanus Remediation Team continued removing sediment near the east side of the Union Street Bridge.
During the week of September 20 the Gowanus Remediation Team continued removing sediment near the east side of the Union Street Bridge.
During the week of September 13 the Gowanus Remediation Team continued removing sediment near the east side of the Union Street Bridge.
During the week of September 6 the Gowanus Remediation Team continued demobilizing the work barges at the Carroll Street Bridge.
During the week of August 30 the Gowanus Remediation Team began demobilizing the pipe pile barge configuration at the Carroll Street bridge.
During the week of August 23 the Gowanus Remediation Team continued pipe pile operations at the Carroll Street bridge.
During the week of August 16 the Gowanus Remediation Team continued pipe pile operations at the Carroll Street bridge.
During the week of August 9 the Gowanus Remediation Team continued pipe pile installation along the canal-facing sides of the Carroll Street bridge abutments.