Progress Update, Week of February 7th, 2022
During the week of February 7 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge.
During the week of February 7 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge.
During the week of January 31, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade and north of the Carroll Street Bridge.
During the week of January 24, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 17, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 10, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 3, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of December 27, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) along the Bond Street Promenade.
During the week of December 20, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) within RTA-1.
During the week of December 13, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) within RTA-1.
During the week of December 6, the Gowanus Remediation Team continued sheet pile bulkhead installation at the head of the canal near Butler Street.