Progress Update, Week of December 5th, 2022
During the week of December 5, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street. Surveying was conducted to review dredging results.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of December 5, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street. Surveying was conducted to review dredging results.
During the week of November 28, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street.
During the week of November 21, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street.
During the week of November 14, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street.
During the week of November 7, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street.
To contact the Gowanus Remediation Team please email info@gowanussuperfund.com or call the hotline at (718) 569-5762.