Progress Update, Week of March 28th, 2022
During the week of March 28 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS). The ISS work barges were relocated to conduct ISS near the Carroll Street Bridge.
During the week of March 28 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS). The ISS work barges were relocated to conduct ISS near the Carroll Street Bridge.
During the week of March 21 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge. At Degraw Street the tieback installations… Read More »Progress Update, Week of March 21st, 2022