Progress Update, Week of March 7th, 2022
During the week of March 7 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.
During the week of March 7 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.
During the week of February 28 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of February 21 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of February 14 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge.
During the week of February 7 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge.
During the week of January 31, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade and north of the Carroll Street Bridge.
During the week of January 24, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 17, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 10, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 3, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.