Progress Update, Week of June 13th, 2022
During the week of June 13, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge.
During the week of June 13, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge.
During the week of June 6, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge.
uring the week of May 30 the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) near the Union Street Bridge. Daily closures were in effect during work between bridge abutments.
During the week of May 23 the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) north of Union Street.
During the week of May 16 the Gowanus Remediation Team (GRT) resumed In Situ Stabilization (ISS) north of Union Street.
During the week of May 2 the Gowanus Remediation Team (GRT) completed Phase 2 dredging near the Union Street Bridge. Sediment was raked following the completion of dredging activities.
During the week of May 2 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge.
During the week of April 25 the Gowanus Remediation Team (GRT) continued phase 2 dredging near the Union Street Bridge.
During the week of April 18 the Gowanus Remediation Team (GRT) continued Phase 2 dredging near the Union Street Bridge.
During the week of April 11 the Gowanus Remediation Team (GRT) conducted In-Situ Stabilization (ISS) near the Carroll Street Bridge early in the week, before temporarily suspending ISS operations in order to commence Phase 2 dredging.