Progress Update, Week of December 27, 2021
During the week of December 27, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) along the Bond Street Promenade.
During the week of December 27, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) along the Bond Street Promenade.
During the week of December 20, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) within RTA-1.
During the week of December 13, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) within RTA-1.
During the week of December 6, the Gowanus Remediation Team continued sheet pile bulkhead installation at the head of the canal near Butler Street.
During the week of November 29, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal.
During the week of November 22, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal.
During the week of November 15, the Gowanus Remediation Team began installing sheet pile bulkheads near the head of the canal.
During the week of November 8, the Gowanus Remediation Team (GRT) continued mobilizing equipment and materials in preparation for sheet pile bulkhead installation work near the head of the canal.
During the week of November 1, the Gowanus Remediation Team (GRT) completed sediment removal at the Union Street Bridge.
During the week of October 25 the Gowanus Remediation Team (GRT) continued the demonstration of In Situ Stabilization (ISS).