Progress Update, Week of March 16th, 2026
During the week of March 16, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued near Bush Street. Installed sheet piles were backfilled. Tieback anchors were installed.
Bulkhead installation continued near 9th Street. Concrete curbwork was performed.
Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed. Grout was placed.
Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed.
Photos of construction activities are provided below.



















